Operation Manual / TPL85-B14/-B15/-B16
Cleaning the compressor during
oper
© Copyright 2016 ABB. All rights reserved.
May 2016 HZTL2491_EN Revision B
Screw in the sealing plug (X).
Push the valve activator (Y) against the spring and hold it for 10 to 15
seconds until the entire volume of water has been injected.
After cleaning, wait at least 5 minutes to allow the turbocharger to dry.
If the cleaning operation is not satisfactory, it may be repeated up to
two times.
If the cleaning results are still not satisfactory after three attempts and
the engine values are also unsatisfactory, we recommend that you have
the turbocharger inspected and cleaned by an official ABB Turbocharg-
ing Service Station.
Cleaning parameters per turbocharger compressor
Contents of water vessel
[dm
3
]