Installation and maintenance instructions UniGear type ZS2 UniSafe-36 1YTW571780-012 Rev:E 01-2005 en Page: 10 of 25
The HD4 breakers are delivered either
in the panels or in separate packing
according to order planning.
The HD4 breaker has the liftingspots
marked and crane-lifting must consider
these spots.
Please refer to Instruction Manual for
HD4W-36kV circuit breakers.
Doc:ITNIE647016/003
Fig:2.3.7 2.3.8 2.3.9
Circuit Breaker Trolley, Fixed height. (Order no:
1YTW572756-101)
Lift the CB manually or using a suitable hoist,
and place it onto the trolley.
Refer to chapt 4.2 of this manual.
Fig:2.3.10 Fig:2.3.11
2.4 Cubicle’s erection
.
!
CAUTION! The encapsulating sheet steel of cubicles may have sharp edges inside and on the roof.
Before erection the highest point of the floor is identified. The erection begins with the left hand cubicle
which is placed in level with the highest point. The cubicles are trestled if necessary in the front, at the back
and the middle along the switchgear. This is made by one or more layers of thin steel plates.
If the cubicle will be mounted against the wall make sure that the bolts for the rear cover are tightened
before fixing the cubicles.
See also 2.5 before the next cubicle is installed. Next cubicle can then be installed and aligned and adjusted
to the first one.
Tighten the cubicles with bolts in the fitting holes close to the front and rear sides. The fixing is made by
M8X25 bolts.
Remaining cubicles should be erected in the same way. When all cubicles are erected the alignment of the
fronts should be checked.
Fig:2.4.1 Fixing points (without arc-vent channel)
Fig:2.4.2 Fixing points (with arc-vent channel)