Installation and maintenance instructions UniGear type ZS2 UniSafe-36 1YTW571780-012 Rev:E 01-2005 en Page: 18 of 25
2.10 End covers
Fig:2.10.1
Ref: ABB dwg:1YTW572721-100
Towards the end of installation assemble the end covers at the right and left extremities .
2.11 Cleaning
After the installation of the main circuit before closing the enclosure covers and doors the cubicles have to
be checked and if necessary carefully cleaned. Busbars insulation, epoxy insulation and bushings should
be wiped dry and vacuum-cleaned.
3 PUTTING INTO SERVICE
All operations for putting into service must be carried out either by ABB personnel or other skilled
personnel authorized by the user organization.
!
CAUTION! Untill putting into service by authorized and skilled personnel the switchgear must not
be energized. The earthswitches must be closed all the time until the regular energising.
Related personnel for putting into service should consider the below referred instructions:
Installation and service instructions, HD4 CHAPTER-8
ABB doc. no: ITNIE647016-003
Installation and maintenance instructions, UniSafe CHAPTER-11
ABB doc. no: ITNIE647647-001