American Beer Equipment 2001 SW 6
th
St.
Lincoln, NE 68522
55
Acceptable Beer Pre-Startup Checklist, American Beer Equipment
Date
Process
Department
Quality Assurance
Product Item#/Sku
Being Produced
Vessel #
Process Leader
Operator
Individual Taking
Pre-Canning Check
Operator
Specific Beer Pre-Start Checklist
Task
Number
Leader
Initials
Operator
Initials
Pre
-
Run/Set
-
Up
Task Description with Specific
Detail Relative to Task, Measurements,
Settings, outcomes critical to quality, safety,
etc.
1 Is the bacteria level on the filler nozzle acceptable?
2 Is the carbonation level of the beer acceptable?
3 Is the dissolved oxygen of the beer acceptable?
4 Is the brite tank pressure correct?
5 Is the entire CIP chemical out of the beer line?
9 Has foam been bled out of the lines?