AT-GS950/8, AT-GS950/16, and AT-GS950/24 Switches Installation Guide
37
Installing the Switch in an Equipment Rack
To install the switch in a standard 19-inch equipment rack, perform the
following procedure:
1. If the rubber feet are attached to the bottom of the switch, remove
them using a flat-head screwdriver.
2. Attach the two rack mount brackets to the sides of the switch using the
eight bracket screws that come with the unit. There are four possible
positions in which the brackets may be installed.
Figure 6. Attaching the Rack-Mount Brackets to the Switch