6
INSTALLATION & COMMISSIONING
2. Installation & Commissioning Checklist (For Installers Only)
Following the SMILE B3 Plus installation, you must ensure the below checklist is
completed and a record of the same is shared with your system provider. It’s also
recommended to retain records of the equipment installed.
No. Items Description
1 System Provider (Contact details)
2 Primary Batteries Model Number - SMILE-B3 PLUS (5.04
kWh)
S/N –
3 Secondary Batteries Model Number – SMILE-BAT-5P (5.04
kWh)
Number of batteries -
S/N –
S/N –
S/N –
S/N –
S/N –
4 Energy Meters Model Number – ACR10R / DTSU666
Number of Meters –
5 Total Battery Storage Capacity (kWh)
6 UN Number UN 3480
7 Date of Installation & Commissioning
8 Firmware Versions
• Inverter
• BMS
9 Initial System Settings
• Safety Regulation
• Regional Application Standard
AS 4777.2
Australia A / Australia B / Australia C /
NZ
10 System Verication Grid Status - On Grid Status - Off
Is the Battery Charging? (Y/N) N/A
Is the Battery Discharging? (Y/N)
11 If Backup/UPS is Connected, does
the battery discharge towards
connected loads when Utility grid is
turned off? (Y/N)
12 DC Connections – Is there any high
resistance at the junction of the DC
cables & battery terminals? (Y/N)