Step Action
1 The gear casing, motor support and air receiver supports are secured to the frame,
immobilizing the vibration dampers during transport.
2 Remove the bushes (1) from the gear casing supports and the motor support.
3 Remove the brackets fitted next to the air receiver supports.
Electric cabinet
Step Action
1 Check that the electrical connections correspond to the local codes. The installation
must be earthed and protected by fuses in all phases. An isolating switch must be fitted.
2 Check the wires on the transformers for correct connection.
3 Check the setting of the circuit breakers.
In the cabinet door, a filter is foreseen. Sufficient ventilation is guaranteed.
Water circuit
Step Action
1 Check that the cooling water drain valves (customer’s installation) in the inlet and outlet
lines are closed.
2 Check that the water shut-off valves (customer’s installation) are open.
3 Open the water regulating valve and check for water flow.
Start up
On Full-Feature compressors, switch on the voltage 4 hours before starting in order to
energize the crankcase heater of the refrigerant compressor.