INSTALLATION
CHECKLIST
09
33
CHECK
MARK
SECTION INSTALLATION STEP PAGE
COMPONENTS
Components such as fans, dehumidifiers and lights
installed.
All wired to correct colored output according to function.
Wiring fastened to be out of the way.
14
11-12
20
Any accessory components such as vent covers
installed, and space properly secured.
TESTING
RED output testing started.
Each fan physically checked for operation.
28,31
ACE Only
If selected, ORANGE output testing started.
Each fan physically checked for operation.
28
ACE Only
If selected, YELLOW output testing started.
Dehumidifier physically checked for operation.
28
ACE Only
If dehumidifier installed, manufacturer’s instructions
followed, and condensate drainage addressed.
If selected, GREEN output testing started.
Each light physically checked for operation.
29, 31
NOTIFICATIONS
No solid alert light illuminated on the display. 6
Any flashing alert light has been reviewed. 6