MAINTENANCE TIME
Part description Action to be performed Gas
COMBUSTION HEAD
ELECTRODES
VISUAL CHECKS, CERAMIC PARTS INTEGRITY, EDGES SMOOTHING, DISTANCE CHECK,
ELECTRICAL CONNECTION CHECK
YEARLY
IONISATION PROBE
VISUAL CHECKS, CERAMIC PARTS INTEGRITY, EDGES SMOOTHING, DISTANCE CHECK,
ELECTRICAL CONNECTION CHECK
YEARLY
COMBUSTION HEAD COMPO-
NENTS
INTEGRITY VISUAL CHECK FOR ANY MESH DEFORMATIONS, CLEANING YEARLY
INSULATING GASKETS SEAL VISUAL INSPECTION AND POSSIBLE REPLACEMENT YEARLY
AIR / GAS LINE
AIR GRILLE CLEANING YEAR
VENTURI CLEANING YEAR
FAN FAN AND SCROLL CLEANING YEAR
AIR PRESSURE SWITCH CLEANING YEAR
GAS FILTER REPLACING THE FILTERING ELEMENT YEAR
GAS PRESSURE SWITCH CLEANING YEAR
HYDRAULIC/GAS SEALS CHECK OF ANY LEAKAGES YEAR
VARIOUS COMPONENTS
ELECTRICAL SYSTEM CONNECTION CHECK, TIGHTENING OF TERMINALS AND SOCKETS YEAR
EQUIPMENT DISPLAY INTEGRITY CHECK YEAR
COMBUSTION PARAMETERS
CO CONTROL COMPARISON WITH VALUES RECORDED AT SYSTEM START-UP YEAR
CO2 CONTROL COMPARISON WITH VALUES RECORDED AT SYSTEM START-UP YEAR
NOX CONTROL COMPARISON WITH VALUES RECORDED AT SYSTEM START-UP YEAR
IONISATION CURRENT CON-
TROL
COMPARISON WITH VALUES RECORDED AT SYSTEM START-UP YEAR
SMOKE TEMPERATURE
CONTROL
COMPARISON WITH VALUES RECORDED AT SYSTEM START-UP YEAR
GAS PRESSURE REGULATOR PRESSURE MEASURED AT START-UP YEAR
IMPORTANT
In case of heavy-duty operation or when using special fuels, the maintenance intervals must be reduced adapting them to the real opera-
ting conditions, according to the indications of the maintenance technician.
ENGLISH
31 / 40
0006160310_202001