XPR-10 Series Two-Post Lifts 35 P/N 5900951 — Rev. D — May 2019
9. Plumb each Post; install any needed Shims or the optional Adapter Trays (which let you stack the
provided Auxiliary Adapters — also called Extenders — conveniently near the Lift Arms).
Tip If you are going to torque the Anchor Bolts later so that installing the Overhead Assembly
and doing final leveling is a little easier, skip the next step. Instead, make sure the Anchor
Bolts are securely in position; you do not want the Posts moving too much during the
rest of the installation procedure.
10. Wrench each Nut
clockwise
to the recommended installation torque, 110 – 150 foot pounds,
using a Torque Wrench.
Important: Do
not
use an impact wrench to torque the Anchor Bolts.
Wrenching the Nut forces the Wedge up, forcing out the Expansion Sleeve and pressing it tightly
against the Concrete.