EasyManuals Logo

Boge C 15 User Manual

Boge C 15
76 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #42 background imageLoading...
Page #42 background image
Installation 3.5 Commissioning
Page 34 BOGE Operating instructions for C 15 series screw compressors
3.5 Commissioning
Checking installation
requirements
Checking the rotational
direction
NOTICE!
We recommend the drawing up of a commissioning certificate in which the
test results during the commissioning process can be listed up.
WARNING: Risk of injury!
The commissioning may only be carried out by experienced and authorized
qualified personnel!
Always wear protective gloves when working on the compressor to avoid
bruising of fingers or hands while opening or closing components!
WARNING!
Make sure that the compressor is installed according to the installation re-
quirements!
Prior to starting the compressor for the first time, check if the transport secur-
ing device was duly removed and the GM belt tensioning device activated
(see chapter „3.3 Installation“)!
List up the test results in the commissioning certificate.
WARNING!
Always check the rotational direction of the drive motor prior to commission-
ing/initial start up.
Even brief operation in the wrong direction of rotation (more than approx.
5 seconds) may cause total destruction of the air end!
List up the test results in the commissioning certificate.
WARNING!
Ensure that the rotational direction coincides with the rotational direction ar-
row on the air end.
Close mains disconnecting device.
Switch the compressor on and immediately off again to check the rota-
tional direction.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Boge C 15 and is the answer not in the manual?

Boge C 15 Specifications

General IconGeneral
BrandBoge
ModelC 15
CategoryAir Compressor
LanguageEnglish

Related product manuals