THT-100
38
Boon Edam Inc.
402 McKinney Parkway Version: Rev A6 10/28//2011
Tel. 910-814-3800 fax 910-814-3899 Issue: THT-100-IMM-USA
Electrical
Check the safety functions of unit (speed control, heel guards etc., if equipped).
Perform a function test, ACS controls.
Check the operation of the solenoids.
Check earth grounding.
Check the electrical wiring connections, especially for damage near moving parts.
Mechanical
Check the anchor mountings and fasten where needed.
Check the movement of bottom bearing and mounting anchors. Lubricate bearing
through grease zerk.
Check the whole installation for correct alignment with floor (surroundings)
Inspect locking pawls for wear. Ensure they properly lock and hold.
Inspect Key override functions
Inspect Fire Alarm functions (if connected)
Inspect Power failure functions
Inspect Dampening system (if equipped) to ensure rotor arms rotate and rest smoothly.