p. 11 - Manual FA01274-EN - 11/2018 - © CAME S.p.A. - The contents of this manual may change, at any time, and without notice. Original instructions
If the rack is already there, place the anchoring plate, being careful to respect the measurements shown in the
drawing.
Fill the foundation frame with concrete. The plate must be perfectly level with the bolts which are entirely above
surface.
Wait at least 24 hrs for the concrete to solidify.
Fit the bolts into the anchoring plate and tighten them using the nuts. Remove the pre-shaped clamps using a
screw driver or pliers.
Fit the plate into the iron cage. Careful! The tubes must pass through their corresponding holes.