Install Machine Supports
The 19FA machines are typically placed directly on a level floor and do not require isolation
equipment. Check job data for specific information. The standard contact surfaces for floor
mounting are shown in Figure 5 and Figure 6.
When isolation pads are specified by the customer, 7 shear flex pads are shipped with the
machine and strapped to the cooler shell. These pads are placed under the machine base as
shown in Figure 5 and Figure 6. If desired, the base may be anchored through four 1 1/2 in.
Click here for Figure 3 — Machine Rigging Guide
Click here for Table 1A — Rigging and Operating Weights — English (lb)
Click here for Table 1B — Rigging and Operating Weights — SI (kg)
Click here for Figure 4 — 19FA Dimensions

Other manuals for Carrier 19FA Series

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Carrier 19FA Series and is the answer not in the manual?

Carrier 19FA Series Specifications

General IconGeneral
BrandCarrier
Model19FA Series
CategoryChiller
LanguageEnglish

Related product manuals