11-18
Point Operation
[Point 1]
Installation:
Comply with the sizing indicated in the figure to the side
X = 240 mm (mast height 4310);
X = 240 mm (mast height 4505);
X = 320 mm (mast height 5000);
X = 440 mm (mast height 5510);
X = 500 mm (mast height 6005);
X = 620 mm (mast height 6500)
[Point 2]
Installation:
Prevent the pipes from rotating on their axis when
raising/lowering
Important:
Prevent any pipes kept under pressure from causing
a hazard during raising/lowering