Start-up sequence
Unit power supply ON
Before powering the unit carry out a leak test with suitable instrumentation
6 - START-UP
Yes / No
1
compressor carter resistances operating at least since 8 hours
2
off-load voltage measure
3
phase sequence check
4
pump manual start-up and flow check
5
refrigeration circuit shut-off valves opening (if applicable)
6
unit ON
7
load voltage measure
8
verify the lack of bubbles in the liquid light (if applicable)
9
check of all fan operating: no abnormal noises or vibrations
10
measure of return and supply water temperature
11
super-heating and sub-cooling measure
12
run tests in both heat and cool mode (only for heat pump units)
13
check no anomalous vibrations are present
14
set-point personalization
15
scheduling customisation
16
check that all panels are closed and fastened properly
17
complete and available unit documentation