Loading cycles
The machine is expected to live for 40.000 working cycles
1
(i.e. 10 years,
40 weeks per year, 20 hours per week, 5 cycles per hour).
Within this term, the machine must undergo at least 2 (two) in-depth
checks (structural, mechanical, electric, elements, etc.), In case of
particular heavy uses (frequent use at the performance limit, particular
unfavorable environmental conditions such as steel systems, paper mills
and so on) it is better to increase the checks. Anyway it is advisable to
have the state of the machine checked by the manufacturer factory or by
an authorized assistance point, at least every 1500 – 2000 working
hours or once a year
1
Loading cycle: cycle starting from the access position, performing the work and
returning to the access position.