Important Steps of MainsPro utilization
This process describes a typical decisions and technical steps to follow in case of MainsPro utilization,
if required by the distribution network operator (DNO).
Does the DNO
require a mains-
protection unit? If
yes, then...
Request the
required protection
settings from the
DNO
Install MainsPro
according to the
MainsPro
Installation and
Operation Guide
Disconnect the relay
output connectors to
avoid misoperation
of the connected
devices
Adjust setpoints
according to the DNO
requirement and your
site design
Power-down
MainsPro, connect all
terminal connectors
and power-up again
Provide witnessed
commissioning tests
and seal the unit if
required by the DNO
Energize your
generator and
synchronize!