Operating instructions
7
4.1 Transportation of the packed machine
(floor models)
The packing has been projected to assure at the machine the highest protection.
It is therefore suggested to transport the machine while it is packed as near as possible
at the place where it will be installed.
To carry the packed machine, use an elevator, or a bench trolley, inserting its forks in the
basement’s holes.
4.2 Unpacking
Unpack the machine and carefully check it. In case of doubt, do not use it, and call the
Seller.
- cut the straps and remove the cardboard box from the top;
THE OPENING OF THE LATERAL PANEL IS ONLY ALLOWED TO THE ASSISTANCE SERVICE OR TO QUALI-
FIED TECHNICIANS AND MUST BE MADE BEFORE CONNECTING IT. MAKE SURE NOT TO DAMAGE THE
INTERNAL PARTS OF THE DEVICE.
- Remove both the lateral panels unscrewing the relevant fixing screws [21];
- Find and unscrew the bolts [22] which fix the machine’s frame at the packing’s basement;
The outlet of the supply cable is placed on the machine’s lower side. During the lifting make sure
not to damage it.
- Lift the machine from the basement, possibly working on the lower side, near the wheels, and however, only on the
frame’s carrying parts. Remove the basement, and lean the machine on the floor avoiding bumps;
DO NOT insert objects, ropes or brackets for the lifting THROUGH the machine, since these
could damage the inside parts.
- Re-close the lateral panels;
- Replace or move the packing, which is produced with entirely recyclable materials ( ).
5INSTALLATION
THE INSTALLATION MUST BE CARRIED OUT ONLY BY THE ASSISTANCE SERVICE OR BY TECHNI-
CALLY AUTHORISED PERSONNEL AND IN COMPLIANCE WITH THE LAWS IN FORCE, ALWAYS FOL-
LOWING INSTRUCTIONS OF THE MANUFACTURER.