8 | Piping installation
Installer reference guide
94
EVLQ05+08CA + EHYHBH05A + EHYHBH/X08A + EHYKOMB33AA
Daikin Altherma hybrid heat pump
4P355634-1G – 2022.09
1 Insulate and fix the refrigerant piping and cables as follows:
a Gas pipe
b Gas pipe insulation
c Interconnection cable
d Field wiring (if applicable)
e Liquid pipe
f Liquid pipe insulation
g Finishing tape
2 Install the service cover.
8.4 Charging refrigerant
8.4.1 About charging refrigerant
The outdoor unit is factory charged with refrigerant, but in some cases the
following might be necessary:
What When
Charging additional refrigerant When the total liquid piping length is
more than specified (see later).
Completely recharging refrigerant Example:
▪ When relocating the system.
▪ After a leak.
Charging additional refrigerant
Before charging additional refrigerant, make sure the outdoor unit's external
refrigerant piping is checked (leak test, vacuum drying).
INFORMATION
Depending on the units and/or the installation conditions, it might be necessary to
connect electrical wiring before you can charge refrigerant.
Typical workflow – Charging additional refrigerant typically consists of the following
stages:
1 Determining if and how much you have to charge additionally.
2 If necessary, charging additional refrigerant.
3 Filling in the fluorinated greenhouse gases label, and fixing it to the inside of
the outdoor unit.
Completely recharging refrigerant
Before completely recharging refrigerant, make sure the following is done:
1 All refrigerant is recovered from the system.
2 The outdoor unit's external refrigerant piping is checked (leak test, vacuum
drying).
3 Vacuum drying on the outdoor unit's internal refrigerant piping is performed.