EasyManua.ls Logo

Daikin Altherma HT - Test Operation; Procedure and Outline

Daikin Altherma HT
292 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
Test Operation ESIE09-08B
70 Test Operation
1. Test Operation
1.1 Procedure and Outline
Follow the following procedure to conduct the initial test operation after installation.
1.1.1 Check Work Prior to Turn Power Supply On
Check on refrigerant piping
(V3180)
Check on amount of refrigerant
charge
Check air tight test and vacuum
drying
Check on water piping
Check the below items.
Power wiring
Control transmission wiring
between units
Earth wire

Table of Contents

Other manuals for Daikin Altherma HT

Related product manuals