Start-up Checklist
*Store in job le
Date: ________________________________
________________________________
________________________________
Technician: ________________________________
Location: _______________________________________
_______________________________________
_______________________________________
Unit #: _______________________________________
Pre Start-Up
(Check each item as completed)
Verify condensate connection is installed per installation instructions.
Verify proper clearance around the unit for safety, service, maintenance and proper unit operation.
Check gas piping for leaks.
Repair if necessary.
Check all electrical connections and terminals. Tighten as needed.
Verify the scroll compressor(s) are rotating in the right direction.
Verify all accessories are installed and operating correctly.
Verify the installation of the thermostat.
9/2014