Inspecting and Handling the Unit Si39-303
164 Installation Manual
4. Inspecting and Handling the Unit
At delivery, the package should be checked and any damage should be reported immediately to
the carrier claims agent.
When handling the unit, take into account the following:
1. Fragile, handle the unit with care.
Keep the unit upright in order to avoid compressor damage.
2. Choose the path along which the unit is to be brought in ahead of time.
3. If a forklift it to be used, pass the forklift arms through the large openings on the bottom of
the unit.
4. Lift the unit preferably with a crane and 2 belts of at least 8m long.
5. When lifting the unit with a crane, always use protectors to prevent belt damage and pay
attention to the position of the unit’s centre of gravity.
6. After installation, remove the transport clasps attached to the large openings.
7. Bring the unit as close to its final installation position in its original package to prevent
damage during transport.
1.Packaging material
2.Forklift
3.Opening (Large)
4.Belt sling
5.Opening (Small) (40×30)
6.Wear plate
7.Removal of shipping brackets
8.Shipping bracket (Remove the screws.)
RXYQ5
.
8
.
10 type RXYQ12
.
14
.
16 type
RXYQ5 type
6
3
2
4
8
<
7
>
4
4
6
3
RXYQ12
.
14
.
16 type RXYQ8
.
10 type
1
1
6
3
4
2
5
4
1