ED34-862 Installation
FXSQ-M 225
6
(2) After piping work is finished, check drainage flows smoothly.
• Open the water inlet lid, add approximately
1 liter of water gradually and check drainage flow.
Open
Water inlet
Portable pump
Water inlet lid
Refrigerant pipes
Close
Bucket
Drain outlet for maintenance
(with rubber plug)
Note: Use this outlet to drain water from the drain pan.
Adding water from
inspection opening
[ WHEN ELECTRIC WIRING WORK IS FINISHED ]
•
Check drainage flow during COOL running, explained under “TEST OPERATION.”
[ WHEN ELECTRIC WIRING WORK IS NOT FINISHED ]
•
Remove the electric parts box lid, connect a power supply and
remote controller to the terminals.
(Refer to the “HOW TO CONNECT WIRINGS”)
Next, press the inspection / test operation button “ ” on the
remote controller. The unit will engage the test operation mode.
Press the operation mode selector button “ ” until selecting FAN
OPERATION “ ”. Then, press the ON/OFF button “ ”. The
indoor unit fan and drain pump will start up. Check that the water
has drained from the unit. Press “ ” to go back to the first mode.
•
You can check whether drainage is satisfactory or not by removing
the access opening lid and checking the
water level of the drain pan through the access opening.
• Be careful when doing so because the fan is turning at the same time.
L N
X Y
NL
Electric parts box
220V – 240V single
phase power supply.
Indoor
PC board
TEST
TEST
3P086156-7D
Power supply
terminal block
Be sure attach the electric parts box lid before turning on the power.