www.DaikinApplied.com 25 IOM 1274-3 • CENTRIFUGAL WATER CHILLERS

Compressor(s), power box(es), and control box are removed at the factory and shipped on separate skids; combined vessel stack
is shipped together as a sub-assembly.
Figure 20: Partial Disassembly Construction Option - Representative Schematic
Scope:
Site reassembly must be supervised or completed
by Daikin Applied service personnel. Cost for unit
reassembly and supervision by Daikin Applied service
is not included in the purchase price of the equipment.
Contact Daikin Applied service for pricing.
Unit is fully tested at the factory prior to disassembly and
shipment.
All associated piping and wiring remain attached, if
possible. Suction and discharge lines have bolt-on

or weight dictates further disassembly, the vessels can
be separated by disconnecting any interconnecting wiring
and tubing and then unbolting them.
Refrigerant will not be shipped with the chiller and must
be procured by others. Compressor(s) and vessels
receive an inert gas holding charge that must be released
prior to attempting to open any connection.
󰀨
compressor and vessel openings.
Unit ships with vessel and/or head insulation, if ordered.
Unit ships with replacement refrigerant gaskets and
O-rings, stick-on wire ties, and touch-up paint.
CAUTION
Standard torque specs must be followed when re-installing
bolts. Contact Daikin Applied service for this information.
WARNING
Remove compressor, piping or vessel holding charge
󰀨

can cause severe bodily injury.
VIEW 1
SUCTION & DISCHARGE
BLOCKOFF PLATES
HOT GAS BYPASS
(OPTIONAL)
LIQUID LINE
SUCTION
DISCHARGE
VIEW 2
LIQUID LINE & HOT GAS BYPASS
BLOCKOFF PLATES
Interconnecting piping to be crated
along with gaskets, o-rings, clamps,
brackets, and additional unit
hardware:
Oil lines
Liquid injection line
Motor cooling lines
Motor drain line
Suction elbow
Discharge line
Liquid line
Oil cooler refrigerant lines