© Danfoss A/S (RA Marketing/MWA), Nov. 08  RS8FE102, 080R9278    13
OPTYMA
TM
 Control three-phase  Operation and Maintenance Guide
Checks before use
•  Having completed  the  wiring, please  check  with 
  the  wiring  diagram  to  ensure  it  has  been  done  
  correctly.
•  Check that the screw clamping is correct.
•  If  possible,  check  that  the  outside  protection  
  devices function correctly.
•  Calibrate  the  motor  circuit  breaker  for  the  
  compressor (if present) correctly as shown on the  
  following pages.
•  After powering up the control, please check  
  the correct current absorption on the loads,  
  and after it has been running for a few hours  
  check that the screws on the terminal blocks  
  are sufficiently tight (including power supply  
  line connection).
  Warning: 
  Please disconnect the power sectioning power  
  supply upstream of the line and secure it with  
  a padlock for max. safety, before tightening 
  the screws. Before any operation, use a  
  voltage detector to check that there is no  
  voltage.