Maintenance 5.2 Routine maintenance work plan
Intervals Maintenance Activity Plan executed by: Comments
with/after levels
50 [OH] E 10 after operation and E 50 - E 70 authorised specialised staff
daily E 20 daily inspection the user
250 [OH] E 25 Inspection authorised specialised staff
500 [OH] E 30 further inspection authorised specialised staff
1000 [OH] E 40 intermediate repair authorised specialised staff
3000 [OH] E 50 further intermediate repair authorised specialised staff
6 000 [OH] E 60 partial repair authorised specialised staff
12 000 [OH] E 70 major repair authorised specialised staff
5.2.1 Routine maintenance work plan