Eaton 9395XC UPS 1200kW/1200kVA, 1350kW/1350kVA or 1500kW/1500kVA 164001079—Rev 01 61
Figure 31. UPS Power Terminal Detail BB
Section B-B
UPS Input, E2
UPS Input, E1
UPS Input, E3
FRONT
Battery
Input (+) E4
Battery
Input (-) E5
2. Using hardware from the external wiring terminal hardware kit (see Table 9), connect the positive,
negative, and ground DC power wiring from the battery systems or disconnects to the ISBM section
battery and ground terminals. See paragraph 3.2.4 UPS System Power Wiring Preparation for wiring and
termination requirements.
3. After wiring the UPS system to the facility power and critical load, be sure to ground the system according
to local and/or national electrical wiring codes.
4. When all wiring is complete, reinstall the conduit panel removed in 4.6.1 External Power Wiring Installation
Step 2 and secure with the retained hardware.
5. Reinstall the panels removed in paragraph 4.6.1 External Power Wiring Installation, Step 1 and secure with
the retained hardware.
UPS System Installation