Installation
Eaton BladeUPS 12 kVA Maintenance Bypass Cabinet Installation and Operation Manual P-164000130—Rev 1 www.eaton.com/powerquality 3-11
1. Ensure the UPS indicator is green, signifying that the UPS is on and operating normally.
2. From the Start screen, press any button to activate the menu options (see Figure 3-6).
l
Use the two middle buttons ( and ) to scroll through the menu structure.
l
Press the button to enter a submenu.
l
Press the button to select an option.
l
Press the
ESC
button to cancel or return to the previous menu.
Power On Indicator (green)
On Battery Indicator (yellow)
Bypass Indicator (yellow)
Alarm Indicator (red)
Control Buttons
for the LCD Menu Options
Figure 3-6. Eaton BladeUPS Front Panel LCD Display
3. Go to the Settings menu.
4. Select User
Settings.
5. Select Si
gnal Inputs.
6. Select signal input 1 or 2.
- Select 1 or 2 based on which terminal was used to connect the signal input wiring.
7. Select Fo
rce Bypass.
8. Press the
ESC
button to return to the Start screen.
3.4 Starting Up the MBC
Although this unit can be started by any knowledgeable contractor or end user, Eaton offers optional startup
and maintenance contracts using factory authorized service personnel
3.5 Completing the Installation Checklist
The final step in installing the MBC is completing the following installation checklist (see the Appendix A.1,
“Installation Checklist”). This checklist ensures that you have completely installed all hardware, cables, and
other equipment. Completing all items listed on the checklist will ensure a smooth installation. Make a copy of
the installation checklist before filling it out, and retain the original.
If an optional startup service is purchased and the install
ation is complete, a service representative will be able
to verify the UPS system operation and commission it to support the critical load. The service representative
cannot perform any installation tasks other than verifying software and operating setup parameters. Service
personnel may request a copy of the completed installation checklist to verify that all applicable equipment
installations have been completed.
NOTE The installation checklist MUST be completed prior to starting the UPS system for
the first time.