Commissioning Ceraphant T PTC31, PTP31, PTP35
16 Endress+Hauser
6 Commissioning
6.1 Function check
Carry out a post-installation and a post-connection check as per the checklist before
commissioning the device.
• "Post-installation check" see Chap. 3.3 checklist
• "Post-connection check" see Chap. 4.6 checklist
6.2 Basic settings
Base Basic settings
Technical unit Select technical unit:
bar
psi
kPa/MPa
%
Configure zero point Offset:
±20 % URL
Accept zero point Current value as zero point (Offset
max. ±20 % URL)
Display PV
1)
: measured value display
PVRO: measured value display
rotated 180°
SP: set switch point display
SPRO: set switch point display
rotated 180°
OFF: display off
OFFR: display off rotated 180°
Damping:
display value, output signal
0...40 s
in increments of 0.1 s
DESINA
Factory setting: NO
Connection in accordance with
DESINA guidelines
(see Chap. 4)