24
c. Check the strings for ground faults.
NOTE:
HighcurrentscandamagetheEnnityinverter!
•ThemaximumpossiblecurrentperDCplugmaynotexceed16A.
d. Connect the DC plug connectors.
e. Close unused input sockets with the sealing caps included in the packing list.
f. Check that all PV panels are connected to the inverter correctly, DC connectors which are not used
should be sealed by cover.
•Startinverter
a. First turn on DC, next, switch on the AC side.
b. Inverter will start up automatically when PV panels generate enough energy. Below are three dierent
states when operating, which means the inverter is starting up.
Waiting: Inverter is waiting to check when output DC voltage from PV panels is greater than 100V
(lowest start-up voltage) but less than 150V (lowest operating voltage).
Checking: Inverter will check output environment automatically when DC output voltage of PV panels
exceeds 150V and PV panels have enough energy to start inverter.
Normal: Inverter begins to operate normally with lights-on. Meanwhile, the LCD displays present
output power.
Inverters will work in MPPT mode when PV voltage is in the MPPT voltage range, range, the inverter
will stop producing power to the grid when PV power is not enough.
NOTE:
If inverter shows ‘Fault’ status, please refer to Part 10.