Performing Concluding Routines
4 Performing Concluding Routines
Proceed with the instructions in the work order or in the OPerational Instructions
(OPI) that refers to this OPI.
The RBS main unit replacement procedures have been performed as described
in the Installing RBS and other relevant documentation for cabling, spare parts,
and so on, have been followed and required work performed.
Before leaving the site, perform the following procedure:
1. Ensure that the RBS is operational and that no alarms are active.
(Information about optical indicators, can be found in Indicators, Buttons,
and Switches and RBS Description.)
Note: Reaching final optical indicator status can take up to 30 minutes.
2. Save the configuration backup, if applicable.
3. Exit the software application and disconnect the terminal, if applicable.
4. Disconnect the ESD wrist strap, if applicable.
5. Collect all tools.
6. Inform the OMC that work is finished at the node site.
7. Close and lock the main unit, if applicable.
8. Complete the work order.
9. Follow the procedures for the return and disposal of replacement parts and
the disposal of packing. Information about how to handle faulty equipment
can be found in Handling Faulty Equipment.
41
81/1543-LZA 701 6001 Uen B | 2012-11-09