14. Check and test
14-1. Check run
The check run is a function to screen and detect any wiring errors.
After carrying out the check run, you can use the automatic wiring correction function to correct
the wiring.
Normal operation is possible without using the check run. In this case, use the test run or
forced cooling function of the indoor unit to confirm any wiring errors.
¢
Things to confirm before starting the check run
To ensure safety, check that the following work, inspections and operations have been com-
pleted.
Check item Check column
1
Check that all work on the piping connecting the outdoor unit, indoor units has
been completed.
2
Check that all work on the wiring connecting the outdoor unit, indoor units has
been completed.
3
Is there a gas leakage? (At pipe connections [flange connections and brazed
areas])
4 Is the system charged with the specified volume of refrigerant?
5 Is a breaker installed at the power supply cable of outdoor unit?
6
Are the wires connected to the terminals without looseness, and in accordance
with the specifications?
7 Is the 3-way valve of the outdoor unit open? (Gas pipe and liquid pipe)
8 Is the power supply connected for more than 12 hours?
¢
Restrictions applicable when performing the check run
When the check run starts, all indoor units connected to the outdoor unit will start to run auto-
matically. During the check run, you cannot check the operation of the indoor units separately.
After the check run, check the operation of the indoor units separately in normal operation.
The check run can be used when the temperature is within the operable temperature of the air
conditioner.
In the check run, the air conditioner will automatically switch between cooling and heating de-
pending on the external temperature and internal temperature.
The check run can be completed in about 30 minutes (cooling) or about 1 hour (heating), but
may take more depending on the external and internal temperature conditions etc.
Do not conduct the check run with all the windows in the room closed.
Otherwise the room temperature could get too low or too high.
Depending on the difference of the room temperature of each room, a judgment may be impos-
sible.
Check run is a special operation so there may be a noise louder than the normal refrigerant
noise or a creaking noise.
- 329 -
OUTDOOR UNIT
AOYG36LBLA5

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Fujitsu AOYG36LBLA5 and is the answer not in the manual?

Fujitsu AOYG36LBLA5 Specifications

General IconGeneral
TypeAir conditioner outdoor unit
Multi-splitNo
Product colorWhite
Compressor typeRotary
Gas hose diameter9.52 mm
Hose length (max)80 m
Hose length (min)25 m
Inverter technology-
Liquid hose diameter6.35 mm
Refrigerating mediumR410A
Air conditioner functionsCooling, Heating
Cooling capacity in watts (max)12500 W
Heating capacity in watts (max)14000 W
Heating capacity in watts (min)3500 W
Cooling capacity in watts (nominal)- W
Operating temperature (cooling) (T-T)-10 - 46 °C
Operating temperature (heating) (T-T)-15 - 24 °C
AC input voltage230 V
AC input frequency50 Hz
Design load (cooling)- kW
Hourly energy consumption (cooling)- kWh
Indoor unit noise level (high speed)- dB
Outdoor unit depth370 mm
Outdoor unit width970 mm
Outdoor unit height998 mm
Outdoor unit weight94000 g
Outdoor units quantity1
Outdoor unit noise level67 dB
Outdoor unit sound power level68 dB