Mains and neutral conductor
minimum area
Mains current
up to
16 AWG or 1.5 mm
2
10 A
14 AWG or 2.5 mm
2
16 A
12 AWG or 4 mm
2
25 A
Computer requirements
An external computer is not required. ÄKTAprocess is provided with a built-in industrial
computer.
User-supplied accessories and
consumables
The following equipment must be supplied by the user:
SpecificationTool
Used for unpacking the system13 mm wrench (or ratchet
wrench with 13 mm socket)
Used for unpacking the systemElectrical TX25 screwdriver or
power driver with a hexalobu-
lar TX25 bit
Used for unpacking the systemSafety knife
Used during installation, operation and maintenancePersonal Protective Equip-
ment (PPE)
as required, (e.g., gloves, lab
coats, etc.)
Suitably sized vessels to allow collection of liquid for
10 minutes at maximum flow rate, and a suitably
dimensioned waste system.
Buffer and waste vessels
10 ÄKTAprocess Site Preparation Guide 29-1396-55 AA
2 Site preparation overview

Other manuals for GE AKTAprocess

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE AKTAprocess and is the answer not in the manual?

GE AKTAprocess Specifications

General IconGeneral
BrandGE
ModelAKTAprocess
CategoryLaboratory Equipment
LanguageEnglish

Related product manuals