Functional and electrical safety checks: Checkout procedures completion
2000966-542D Dash 3000/4000/5000 8-55
Checkout procedures completion
This completes all tests associated with the checkout procedures.
1. Discharge the test patient admitted during the ECG tests” on
page 8-22.
2. Set all test equipment power switches to the off position.
3. Unplug the patient monitor (or docking station) from AC power.
4. Remove all test equipment from the patient monitor (or docking
station).
5. GE recommends that the qualified personnel performing the tests
should record functional checkout test values in the “Checkliston
page D-1.