COMMISSIONING
56 OI 248 (EN) REV6 /REV7
7.6.10 Operations Counter
Check the operation of the operations counter.
Read the count shown on the counter and enter the values in the
checklist.
7.6.11 Final Tasks
Remove all testing and measuring equipment from the circuit
breaker.
Replace the roof and side panels of the mechanism after work is
completed. Tighten the bolts (6) and nuts (5) to a torque of 17Nm.
Clean up the installation site.
The breaker is ready to be connected to the high voltage system.

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE GL 310 F3/4031 P/VR and is the answer not in the manual?

GE GL 310 F3/4031 P/VR Specifications

General IconGeneral
BrandGE
ModelGL 310 F3/4031 P/VR
CategoryCircuit breakers
LanguageEnglish

Related product manuals