COMMISSIONING
56 OI 248 (EN) REV6 /REV7
7.6.10 Operations Counter
Check the operation of the operations counter.
Read the count shown on the counter and enter the values in the
checklist.
7.6.11 Final Tasks
Remove all testing and measuring equipment from the circuit
breaker.
Replace the roof and side panels of the mechanism after work is
completed. Tighten the bolts (6) and nuts (5) to a torque of 17Nm.
Clean up the installation site.
The breaker is ready to be connected to the high voltage system.