EasyManuals Logo

GE LOGIQ E8 User Manual

GE LOGIQ E8
418 pages
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Page #408 background imageLoading...
Page #408 background image
GE HEALTHCARE
DIRECTION 5394227, 12 LOGIQ S8/LOGIQ E8 SERVICE MANUAL
9 - 34 Section 9-8 - Electrical Safety Tests
9-8-13 e-TRAX Leakage current - Mains to CF Applied part
Reference the procedure in the IEC 60601-1. Measure leakage current flow from mains to CF Applied
part.
9-8-13-1 e-TRAX (sink) Leakage Test Record
Table 9-19 below shows a typical format for recording e-TRAX sink leakage current.
Measurements should be recorded for the full lead combination under each set of test conditions
specified in:
9-11 on page 9-18, or
9-12 on page 9-18 as applicable.
Record all data on the inspection certificate.
Table 9-19 Typical data format for recording e-TRAX (Sink) leakage
DANGER
!! DANGER:
Electric Shock Hazard.
Line voltage is applied to e-TRAX during this test. To avoid possible electric shock hazard, the
system being tested must not be touched by patients, users or anyone during testing.
CAUTION
!! CAUTION:
Equipment damage possibility. Never switch the Polarity and the status of Neutral when the unit
is powered ON. Be sure to turn the unit power OFF before switching them using the POLARITY
switch and/or the NEUTRAL switch. Otherwise, the unit may be damaged.
Unit under test____________________________________ Date of test:_____________________
Test Conditions
e-TRAX Needle SensorSystem Power Grounding/PE
On Closed
Off Closed

Table of Contents

Other manuals for GE LOGIQ E8

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the GE LOGIQ E8 and is the answer not in the manual?

GE LOGIQ E8 Specifications

General IconGeneral
BrandGE
ModelLOGIQ E8
CategoryMedical Equipment
LanguageEnglish

Related product manuals