Example 3:
If your solar inverter is connected to other loads
too far away from the control cabinet with the
go-e Controller, you cannot measure it directly.
As already mentioned, this does not matter for
PV surplus charging.
Below we explain 3 examples of how to congu-
re the categories.
Example 1:
If you have mounted the respective sensor
directly on one phase of the grid connection,
you should set the Grid category to one. If
you do not measure your household con-
sumption separately, you should also set the
Home category to one. This will allocate the
entire current of the measured line directly to
mains supply and household consumption.
If you have mounted a sensor on the line of a
PV inverter, you can assign the power directly to
the solar category. The power should be posi-
tive when the inverter is producing solar pow-
er. If you measure all phases in a single-phase
or three-phase inverter, choose a factor of 1.
However, if you have a three-phase inverter and
Example 2:
Let's assume we measure the load branch
and the inverter on all phases. Then the ca-
tegories correspond to the following picture:
PV
PV
PV
only measure one phase, you can select the factor
3, the Controller then assumes 3 times the mea-
sured power, since we only measure one third.
We now have to assign the solar power to the
home category. Let's take a look at this calcula-
tion example:
• Grid: we draw 1 kW from the grid
• Solar: Solar: we generate 500 W of solar
energy
We have already allocated the 1 kW of grid con-
sumption to Home. However, since we produ-
ce another 500 W ourselves, the total power
we consume in the house is 1.5 kW. Therefo-
re, please also assign the solar inverter to the
Home category with the factor 1 or 3, depen-
ding on the number of measured phases of the
inverter.
We have to subtract the solar production from
the grid, so we have to set the factor to minus one.
If you simply measure a load, for example a
boiler, you can assign it to a custom category,
for example "Custom 1". You can rename the
category later. Assigning it to Grid or Home is
not necessary, as you are already measuring
these currents.
Power grid
Power grid
Power grid
Home
Home
Home
other loads
other loads
distance too far
Sensor 4
Solar: Factor 3
Home: Factor 3
Sensors 1-3
Grid: Factor 1
Home: Factor 1
Sensors 4-6
Solar: Factor 1
Grid: Factor -1
Sensors 1-3
Grid: Factor 1
Home: Factor 1
10a. Commissioning/operation on the device

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the go-e Controller and is the answer not in the manual?

go-e Controller Specifications

General IconGeneral
EnclosurePlastic
Communication InterfaceWiFi
ProtocolsModbus
Output Voltage230 V
Frequency50 Hz
ProtectionOvercurrent, Overvoltage