Goodwe EH Plus Series - Equipment Commissioning; Check before Power on; Power on

Goodwe EH Plus Series
68 pages
Print Icon
To Next Page IconTo Next Page
To Next Page IconTo Next Page
To Previous Page IconTo Previous Page
To Previous Page IconTo Previous Page
Loading...
40
07 Equipment Commissioning User Manual V1.4-2022-08-30
7.2 Power On
7 Equipment Commissioning
7.1 Check Before Power ON
No. Check Item
1
The product is rmly installed at a clean place that is well-ventilated and easy-to
operate.
2
The PE, DC input, AC output, and communication cables are connected correctly and
securely.
3 Cable ties are intact, routed properly and evenly.
4 Unused cable holes are tted using the waterproof nuts.
5
The voltage and frequency at the connection point meet the inverter grid connection
requirements.
Step 1: Turn on the AC breaker on the ON-GRID side of the inverter.
Step 2: Turn on the AC breaker on the BACK-UP side of the inverter.
Step 3: Turn on the battery breaker between the inverter and the battery.
Step 4: Turn on the DC switch of the inverter.