Figure 4 Reagentless chlorine analyzer panel
1 System panel 3 Tubing, 12 mm (½ in.)
2 Connector cable for connecting gateway to
controller, 1 m (3.3 ft)
4 Chlorine sensor
Installation
Installation considerations
Do the mechanical installation tasks first, the electrical installation tasks second, and the plumbing
installation tasks last.
All fittings are designed to be tightened by hand only.
The panel is designed to be wall or rack mounted. Mount or position the panel in an accessible
location.
Do not place the panel next to a heat source.
Do not mount the panel in an environment with frequent vibrations
Do not mount the panel in direct sunlight.
Install the panel indoors or in an environmental enclosure.
Prevent condensation from collecting on the panel and panel components, especially the flow cell,
sensor and where the sensor and cable connect.
Use Teflon
®
or PVDF linear low-density polyethylene tubing for the sample supply line and keep
the tubing as short as possible to minimize lag time.
Sample pressure must be sufficient to keep a continuous water supply to the sensors. An LED
indicator on the flow sensor will be lit as long as the flow is sufficient.
Keep the flow rate as constant as possible for best sensor operation.
Sample line guidelines
Select a good, representative sampling point for the best instrument performance. The sample must
be representative of the entire system.
To prevent erratic readings:
Collect samples from locations that are sufficiently distant from points of chemical additions to the
process stream.
Make sure that the samples are sufficiently mixed.
8