45XA - HLA16PX - 55XA - HLA19PX
C
- Pre-operation inspection
2 - Working area assessment
Before carrying out any operations, ensure that the machine corresponds to the work to be done and
the working environment :
• Carry out a thorough inspection of the site to identify any potential risks within the work zone.
• Take the necessary precautions to avoid collisions with other machinery within the work zone.
Ensure that :
• The weather conditions (wind, rain, etc.) allowing the machine to be used.
• The ground withstands the weight of the machine and has not been affected by the poor weather conditions.
• Check that the authorisations to work with the machine on the site in question have been obtained
(.g. chemical product factories).
• Define a rescue plan for all the risks, including the risk of falls and crushing.
• ALWAYS position away from power lines, this ensures that no part of the aerial work platform
accidentally reaches into an unsafe area. This includes full extension of the telescoping boom
through 350 ° Non-Continuous rotation.