76
11 MAINTENANCE SCHEDULE
(Some points have also been prescribed in accordance with TGPF 118 H!)
For safety reasons, maintenance must only be carried out with the main
switch turned off. However, first of all, the system must be switched off by
means of the On/Off button and you must wait for the burnout phase. If you
have to climb into the storage tank or bunker, always make sure that there
is a second person available to supervise you.
Potential carbon monoxide enrichment may put your life in danger.
Check the whole boiler system (1)
including the fuel storage room (2)
visually for damages and wear.
Repair discovered faults immediately.
Check extinguisher container filling
level.
and refill if necessary. If re-filling
occurs frequently, contact your
contracting party.
every 1–4 weeks
(depending on the
operating hours earlier)
a) Open maintenance cover on both
sides of heat exchanger (HE). If
necessary remove ash.
b) For HE-cleaning, check the
movement of the turbulators and
switch them on via the aggregate
test
c) *In the case of central ash, open
the pusher container
maintenance cover. Check for
slag or foreign objects
d) * Check ash locks for operation
(MAIN MENU - Outputs II + III -
AGGREGATETEST - FAS-ON)
*only at FAS optionally (central de-