Installation Test
Installation Test
Once the unit has been mounted and all wiring connections are
complete, a test of the units functions is recommended. It is necessary
to access the units programming menus to perform the test:
• Power up the unit and allow 5 minutes for the warm-up
procedure to complete (allow 15 minutes warm-up for O
2
sensor).
• Press the enter key on the front touchpad.
• The LCD displays the Password login screen. See Password
Menu.
Once in the programming menus, use the arrow key to scroll to the
TestMode option. See TestMode Menu.
The TestMode menu performs a test of all functions on the unit. All
outputs are activated according to their failsafe mode, relay setting, and
buzzer setting. All functions are activated simultaneously for a maximum
of 3 minutes (or until the user cancels the test) to ensure the unit is
operating correctly.
The unit does not detect gas during the TestMode procedure.
Once all functions are confirmed in good working order, the unit is
completely functional.
Should any function fail the test, verify that all connections are correctly
wired and re-test.