1 Grounding lug
Figure 4: Aruba 4605 Switch grounding lug
1
1 Aruba 4610 Switch grounding lug
Make sure the resistance between the chassis and the ground is less than 1 ohm.
Power
Perform the following tasks to meet the power requirements:
Procedure
1. Calculate the system power consumption. The system power consumption varies by module type and
density. (See System power consumption.)
2. Identify the number of power supplies. Include sucient power to meet power consumption and
sucient redundancy to ensure system uptime in the event of a PSU failure.
3. Verify that the power system at the installation site meets the requirements of the power supplies,
including the input method and rated input voltage. (For power supply unit (PSU) information, see
System power consumption.)