NO TE
The cable diameter must comply with local cable standards. The factors that aect cable
selection include the rated current, cable type, routing mode, ambient temperature, and
maximum expected line loss.
Table 5-2 PE cable specications
Conductor Cross-Sectional Area S of
the AC Power Cable (Unit: mm
2
)
Conductor Cross-Sectional Area S
P
of
the PE Cable (Unit: mm
2
)
S > 35 S
P
≥ S/2
The specications are valid only if the conductors of the PE cable and AC power
cable use the same material. If the materials are dierent, ensure that the
conductor cross-sectional area of the PE cable produces a conductance
equivalent to that of the cable specied in this table. The specications of the
PE cable are subject to this table or calculated according to IEC 60364-5-54.
Connecting the PE Cable
Step 1 Secure the PE cable using the ground screw.
Figure 5-8 Cable connection
Step 2 (Optional) Apply silica gel or paint on the ground terminal to protect it against
corrosion.
----End
Connecting the AC Output Power Cable (Multi-core)
Step 1 Connect the AC cable to the terminal block.
SUN2000-(175KTL-H0, 185KTL-INH0, 185KTL-H1
User Manual
5 Electrical Connections
Issue 05 (2020-08-30) Copyright © Huawei Technologies Co., Ltd. 39