PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
4 Installing Components
Copyright © Huawei Technologies Co., Ltd.
Figure 4-3 Installing an HSU
----End
4.4 Installing an NIM01C3
Prerequisites
If the site requires an NIM01C3, perform the following steps to install it.
Wear ESD gloves during installation.
Procedure
Step 1 Remove the filler panel from the slot for installing the NIM01C3.
Step 2 Gently insert the NIM01C3 into the slot along the guide rails.
Step 3 Push the handle leftwards and tighten the screws.
The NIM01C3 must be installed in the upper slot.