PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
7 Installing Cables
Copyright © Huawei Technologies Co., Ltd.
iBOX
ADDR1
ADDR2
ADDR3
ADDR4
Address
iBOX 16
ON
ON
ON
ON
75
----End
7.6 Installing PV Input Power Cables
Prerequisites
Switch off all circuit breakers before installing power cables.
Procedure
Step 1 Connect DC input power cables between the solar junction box (SJB) and the cabinet.
1. Prepare a cable of suitable length as required and install a cord end terminal or an OT
terminal on both ends of the cable.
2. Secure one end of the negative DC input power cable to the PV- screw in the cabinet.
3. Secure one end of the positive DC input power cable to the PV+ screw in the cabinet.
4. Secure the other end of the DC input power cables to the output terminal in the SJB.
Figure 7-18 Installing PV input power cables
One PV input is used as an example.