PowerCube 5000 (SUN2000-150KTL-S0)
Installation Guide
9 Power-on and Commissioning
Copyright © Huawei Technologies Co., Ltd.
Figure 9-4 MDU main menu
After you press the start/stop button, wait about 45 minutes until the load starts to power on.
----End
9.4 WebUI
9.4.1 Connecting a Communications Cable
Procedure
Step 1 Preparing the Operating Environment.
Step 2 Connect the FE port on the SMU by using a network cable.
Figure 9-5 Connecting a Communications Cable
(1) FE port
----End
9.4.2 Setting Parameters
Procedure
Step 1 Apply to the site or equipment room network administrator for a fixed IP address.