6 Commissioning
6.1 Check Before Power-on
No. Acceptance Criteria
1 The solar inverter is installed correctly and securely.
2 The DC switches and the downstream AC switch are OFF.
3 All cables are connected correctly and securely.
4 Unused terminals and ports are locked by waterproof caps.
5 The installation space is proper, and the installation environment
is clean and tidy.
6 The maintenance compartment door is closed and the door
screws are tightened.
6.2 Powering On the SUN2000
Precautions
NO TICE
Before turning on the AC switch between the SUN2000 and the power grid, use
a multimeter set to the AC position to check that the AC voltage is within the
specied range.
If the solar inverter has been stored for more than two years, it must be
checked and tested by professionals before being put into use.
SUN2000-(100KTL, 110KTL, 125KTL) Series
User Manual 6 Commissioning
Issue 07 (2020-09-15) Copyright © Huawei Technologies Co., Ltd. 69

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-100KTL Series and is the answer not in the manual?

Huawei SUN2000-100KTL Series Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-100KTL Series
CategoryInverter
LanguageEnglish

Related product manuals