Procedure
Step 1 Turn on the AC switch between the SUN2000 and the power grid.
NO TICE
If you perform Step 3 before Step 1, the SUN2000 reports a fault about abnormal
shutdown. You can start the SUN2000 only after the fault is automatically
rectied.
Step 2 (Optional) Remove the screws that secure DC SWITCH 1, DC SWITCH 2, and DC
SWITCH 3. Store the screws properly for future power-o maintenance.
NO TE
For the model used in Australia, perform this step based on the local standards.
Figure 6-1 Remove the screws
Step 3 Set DC SWITCH 1 (MAIN SWITCH) at the bottom of the solar inverter chassis to
ON.
Step 4 1Check the status of the PV connection indicator. If it is steady green, set DC
SWITCH 2 and DC SWITCH 3 to ON.
Step 5 Perform quick settings on the SUN2000 app. For details, see 7.1 Operations with
the App.
----End
SUN2000-(100KTL, 110KTL, 125KTL) Series
User Manual 6 Commissioning
Issue 07 (2020-09-15) Copyright © Huawei Technologies Co., Ltd. 70

Table of Contents

Questions and Answers:

Question and Answer IconNeed help?

Do you have a question about the Huawei SUN2000-100KTL Series and is the answer not in the manual?

Huawei SUN2000-100KTL Series Specifications

General IconGeneral
BrandHuawei
ModelSUN2000-100KTL Series
CategoryInverter
LanguageEnglish

Related product manuals